Tuesday, June 23, 2015

Program, deploy, shoot, pick up, download, repeat.

For the next three weeks the experiment pace is going to be a planned sequence of events with very little wiggle room (although two contingency days are built in the schedule). In essence our schedule consists of five fundamental steps repeated for each profile: 1) seismometer programming, 2) instrument deployment, 3) shooting, 4) instrument pick up, 5) data download.
Like clockwork, everything seems easy when coordination and collaboration of all the people in the science team is efficient and these steps follow each other seamlessly. So far we are on schedule and everything is going well.

1) Seismometer programming

The instruments (RefTek 125 a.k.a. "the Texans") are cable-less single-channel dataloggers that can be deployed for three to five days, recording continuously.
Casey holding a "Texan"
Before we can start working with the instruments, we need to power them. So we sat down and loaded each of the 720 of them with 2 D-cell alkaline batteries.

Loading batteries in the 720 Texans. Now we can start testing/programming the instruments.
The recording parameters (window length, sample rate, etc) are programmed before the Texans are deployed through "bridges" that allow to work on multiple instruments at the same time.

One of the PASSCAL bridges used to program, download and connect with the RT125 Texans seismometers. Each bridge (hub) can simultaneously connect with 15 instruments. We have 15 bridges, so during operations we could program/download 225 instruments simultaneously.
Laptops ready to program the instruments that will go in the ground

Bridget working on 45 instruments. Note the bridge inserted on the back side of the box. These instruments are getting ready to be deployed.
2) Instrument deployment

The ENAM land active-source experiment will acquire data along two profiles, Line 1 (to the north) and Line 2 (to the south). We will start deploying and recording Line 2, which has 705 stations. The seismometers along this profile will be deployed by 8 teams, each consisting of 2 people (a driver and a navigator), armed with seismometers, sensors, GPS, shovel, authorized permits, electric tape, deployment/recovering sheets, leveling bubbles, flags, cleaning rags, plastic bags, cutters, bug spray, gallons of drinking water and a bucket of resilience.

Deployers kits
Before the teams head out to the field, Bridget and Eric have been training them on how to correctly deploy the seismic instruments.
Bridget and Eric, showing how to correctly deploy an RT125
 Each team will deploy ~ 85 instruments over a time window of 2 days. All instruments will have to be in the ground by June 22, 11:00PM, when the first land shot will be fired.
Hannah, Ryan and Casey pondering how it will feel doing this 85 times (or more!) in a 105F weather.
After all details are explained and questions answered, the teams head out to the field to survey their stations. This will be their opportunity to familiarize with their section of the profile, select the location for each station and flag it and enter it in the handheld GPS, so that the following day (deployment day) there will be no need to spend time making decisions about the locations and time can be efficiently spent deploying the instruments.

On deployment day, everybody gets a pretty early start. Teams show up at the instrument center around 5AM to pick up a bit over half of their instruments (in the blue boxes - each box contains 15 Texans), and the head out to the field. Dan, Bridget, Eric and I head out to the instrument center around 4:45AM to make sure they get all they need to do their job and see them off. By 7:30AM all teams have loaded and are off to their tasks.

Seismometers and sensors divided up by deployment team ready to be picked up

Deployment teams arrive at the instrument center to load at the crack of dawn.


More loading

Siwen and James checking equipment before loading it in their vehicles
One last load to go!
The last station went into the ground in the evening of June 22. That same night we will shoot 6 points along Line 2. Shooting will start at 11PM if all goes well, and will take most of the night. More on that tomorrow morning!

4 comments:

  1. Did you start shooting last night? This is pretty exciting -- and interesting to layabout layfellows like me.
    John B.

    ReplyDelete
  2. John, last night we successfully shot 6 points. We started picking up instruments today.

    ReplyDelete
  3. At work today, when describing progress on the ENAM project, I got some funny looks when I said they were hard at work deploying seven hundred Texans in North Carolina.
    Mike B.

    ReplyDelete
  4. "and a bucket of resilience." I love your posts Bix!

    ReplyDelete